DMG MORI LT30: Installation and Air System
Machine delivery, utilities, commissioning preparation and a dedicated compressed-air system.
I coordinated the DMG MORI LT30 installation with Facilities, riggers and the machine supplier, from delivery-route measurements to commissioning preparation. I also designed its compressed-air delivery system.
Delivery and commissioning
- Measured and labeled route obstacles, checking an approximately 90 in transport height against 92 in minimum clearance.
- Coordinated riggers, hatch protection, equipment relocation and delivery access. The machine arrived on July 30, 2026.
- Led Facilities preparation for HVAC readiness, temporary door removal and electrical shutdowns.
- Coordinated the 30 A to 50 A power upgrade, including transformer delivery, wiring, disconnect and fuses, and worked with Facilities, electricians and DMG MORI on commissioning and phase rotation checks.
Compressed-air system
- Designed filtration, oil removal, desiccant drying and pressure regulation.
- Specified a 15 SCFM dryer, afterfilter and shutoff/vent valve for servicing.
- Designed strut and pegboard mounting with brackets, spacers and dryer supports.
- Specified 3/8-in connections, hoses and machine couplings, and coordinated air and argon parts procurement.